4041 Site visit (Bent 3 Pre-bore) Get link Facebook X Pinterest Email Other Apps September 02, 2021 Contractor was onsite to Pre-bore Bent 3Piling onsite match Material CertsContractor placed Piling in holes and filled, will seed them on WednesdayWe hit water during Pre-Bore about 5 feet down Get link Facebook X Pinterest Email Other Apps Comments
Rocksdale Bridge - 10/19/2021 October 20, 2021 1 guy on site today with a truck driver to haul in rock for the road. Cut in ditch line and installed storm pipe for access drive. Read more
Rocksdale Bridge - 8/24/2021 August 28, 2021 Traffic control set and equipment being dropped off. Planning on starting work Thursday. Read more