Rocksdale Bridge - 10/21/2021

Image
Guardrail is getting installed today. Crew had to have some washers delivered that were missed. Delaying things.

Rocksdale Bridge - 10/19/2021

Image
1 guy on site today with a truck driver to haul in rock for the road. Cut in ditch line and installed storm pipe for access drive.

Rocksdale Bridge - 10/18/2021

Image
Crew back to work today. Dirtwork and getting rock in for the road. 3 men.

Rocksdale Bridge - 9/29/2021

Image
Getting started with setting the beams. Rip rap has been installed around the end bents. 3rd beam of the day going on. Almost half way through. Last one on this end of the bridge. Guys getting it lined up correctly. Moved on to the other half to repeat the process. View from the side. Coming together well. Beams are installed.

Rocksdale Bridge - 9/23/2021

Image
View from bent 1. Forms & rebar set and ready for concrete. View of bent 2. Bent 3 pour complete. Smoothing out the surface. View from bent 3. Pouring concrete for bent 1. Pour complete. Smoothing out bent 1.

Rocksdale Bridge - 9/20/2021

Image
Crew working on getting the rebar and forms set. Pouring the bent 2 wall today. View from bent 3. Getting the pour underway for bent 2 wall. Wrapping up the pour. 3 trucks.